Planning is complete for an upcoming electrical shutdown for the University Hall Renovation project.This shutdown is scheduled for Saturday, July 21st, 2018 from 7:00 AM to 12:00 PM.
This will impact normal power to Capital Hall, Bryant-Jordan Hall, the Bryce Main and old Superintendents building.
Notes:
• UA Electrical to coordinate “hot ties” with Alabama Power. This allows for isolation of only the buildings noted above. The Harper Center on Bryce campus will not be impacted
• Capital Hall
o Has back-up emergency generator
o Fire alarm system is on emergency generator and will remain operational
o Fire pump is on emergency generator so the fire sprinkler system will remain operational
o UA HVAC to shutoff and restart equipment
o UA Plumbing – No items of concern noted
o UA Elevator to shutdown and secure the elevators
o Access control (card access) on west side of building will not be operational
o All computers need to be powered down prior to electrical shutdown
• Bryant-Jordan Hall
o Fire Alarm system is on battery back-up and will remain operational
o UA HVAC to shutoff and restart equipment
o UA Plumbing – No items of concern noted
o All computers need to be powered down prior to electrical shutdown
• UA Facilities to perform walk-thru of both buildings once power is restored