Electrical Shutdown – Bryant Denny Stadium , UA Electrical Maintenance

06/02/2018 @ 6:00 AM - 06/05/2018 @ 4:00 PM CDT

This will impact power to the entire stadium.**The Digital Media Center will be brought back online by the emergency power system throughout the duration of the shutdown.  However, the Digital Media Center may encounter a brief power outage at the start and end times of the shutdown.  If this is an issue, the Digital Media Center representative will need to contact Ricky Luker with UA Electrical at 348-3961.
** Daniel Black to verify if all broadcast equipment is on UPS.
Notes:
• This will impact all electrical and mechanical systems
• BDS is on 7 back-up emergency generators
• The Emergency Operations Center will be impacted (EOC is on the back-up emergency system)
• Fire Alarm system is on back-up emergency system
• BDS has (2) fire pumps
• Chillers for the north zone and south zone will be impacted
• West elevators will be out of operation. North, south and east elevators are on the back-up emergency system (Digital Media Center to use Northeast elevators)
• Camera systems/monitoring equipment will be ok per Michael Kelley (note from prior shutdown)
• Access control will not be operational.  Not on emergency system
• The gate control for Zoe’s on south end will be impacted (Shawn T. to raise for the weekend)
• The OIT data closet by the home team locker room is not on the emergency system. No other buildings should be impacted (note from prior shutdown)
Action Items:
• 2 fire pumps impacted – South and East Sides – East side fire pump is on back-up emergency system.  UA Plumbing to verify if the south side fire pump is on the emergency system.  If not, UA Electrical to coordinate with Security Resources about performing fire watch
• UA Plumbing shop to verify if plumbing equipment (booster pumps, sump and grinder pumps, water heaters, ect.) are on the emergency system.  If not, is generator needed? (ask Terry McMillan with UA Electrical)
• UA HVAC to shutdown all mechanical equipment and start-up once power is restored
• UA Elevator Maint. to shutoff and secure all elevators that will not remain operational.  Verify start-up once power is restored
• UA Electrical to notify Stephen Lake 30 min prior to restoring normal power in order to test transfer switch functionality for east elevators
• Shawn Templeton to coordinate with Zoe’s Kitchen
• Due to security risk, building signage will not be posted
• Ricky Luker to submit work orders to shops for building support upon request

Details

Start:
06/02/2018 @ 6:00 AM CDT
End:
06/05/2018 @ 4:00 PM CDT