Electrical Shutdown – AIME Building

03/15/2018 @ 6:00 PM - 03/16/2018 @ 2:00 AM CDT

Notes:• Building has back-up emergency generator
• Fire alarm system is on the emergency power system and will remain operational
• Fire sprinkler system is operated by city water pressure and will remain operational
• UA HVAC to shutoff all mechanical equipment and restart once power is restored
• UA HVAC to check that all fume hoods restart once power is restored
• UA Elev. to shutoff and secure the 2 elevators on 3/15 at 4PM and restart on 3/16 by 6AM
• UA OIT to verify if equipment is connected to emergency power system.  IT equipment may need to remain operational due to tests performed by Hunt Oil employees.  Please confirm this with Renae Sullivan (Building Rep)
• Exterior lighting will be impacted.  UAPD and Security Resources may need to provide extra patrol due to shutdown taking place during nighttime