Electrical Shutdown – Ridgecrest South Outside Air System Replacement , UA# 271-17-1392

06/27/2018 @ 9:00 AM - 2:00 PM CDT

Planning is complete for an upcoming electrical shutdown of Ridgecrest South in order to tie-in power to the new outside air units.This shutdown is scheduled for Wednesday, June 27th, 2018 from 9:00 AM to 2:00 PM.
This will impact all electrical and mechanical systems.
Notes:
• Building is on back-up emergency generator
• Fire alarm system will remain operational
• Fire pump is on the emergency power system and will remain operational
• Mike Largin to contact Ray Bostick and Randy Mathis to discuss details about the data equipment area.  It was mentioned in the meeting that all data equipment and A/C for this area is on the emergency power system and will remain operational
• UA HVAC to shutoff all equipment and verify startup once power is restored
• UA Plumbing to verify impact on all plumbing equipment and verify startup once power is restored
• UA Elevator to shutdown and secure all elevators
• Parking deck roll up doors will not be operational.  They will need to remain in the open position
• The faculty apartment is currently the only room occupied

Details

Date:
06/27/2018
Time:
9:00 AM - 2:00 PM CDT