Water Outage – New Alpha Omicron Pi Chapter House

Planning is complete for a short, 30 minute water outage that should only impact Reese-Phifer Hall and the annex building.  This outage is scheduled for Wednesday, April 11th, 2018 from 7:00 AM to 7:30 AM. There is an existing water line that will need to be relocated in the future to allow for the installation […]

Water Outage – HR Latham Building Renovation

Planning is complete for a short, 30 minute water outage that will impact both domestic and fire water to all buildings north of Ruby Tyler Pkwy on the University Services Campus.    This outage is scheduled for Wednesday, April 11th, 2018 from 5:30 PM to 6:00 PM.   UA Plumbing is aware and will perform […]

Electrical Shutdown – University Services Campus

Planning is complete for an upcoming electrical shutdown of the University Services Campus. • Impacted buildings include: o All buildings north of Ruby Tyler Pkwy o F.C. White Food Service building and Wallace Educational building which are on the south side of Ruby Tyler Pkwy o The New Kitchen for Bryce and the Main Bryce Hospital will not be […]

Water Outage – New Alpha Omicron Pi Chapter House

Planning is complete for another water outage that will impact Reese-Phifer Hall and the Reese-Phifer Annex buildings in order to relocate an existing water line for the subject project.  This outage is scheduled for Tuesday, April 24th, 2018 from 5:00 PM to 9:00 PM.   Notes: • This will impact domestic water only • Does not impact […]

McCorvey Dr. Lane Closure Coordination – Lakeside Dining Hall Renovation

The southbound lane of McCorvey Dr. will be closed from Hackberry Ln. to 2nd St. for approx. 5 hours on Tuesday, April 24th, 2018 in order to setup a concrete truck for an overnight slab pour.This closure will last from 1:00 AM to 6:00 AM (4/24/18). Please see attached map showing the portion of McCorvey […]

Water Outage – Capstone Parking Deck

Planning is complete for an upcoming water outage in order to lower an existing 30” city main so that future storm drainage can be installed for the subject project.  This water outage is scheduled to start on May 21st, 2018 at 7:00 AM and end on May 24th, 2018 at 5:00 PM.   This will […]

Electrical Shutdown – Mal Moore Athletic Facility Dining Addition , UA# 085-16-953

Planning is complete for an upcoming electrical shutdown of the Mal Moore Athletic Facility in order to test the new generator installed under the dining addition project. This shutdown is scheduled for Friday, May 11th, 2018 from 2:00 PM to 5:00 PM. Notes: • The power to Mal Moore Athletic Facility will be off momentarily until […]

Water Outage – Mal Moore Athletic Facility Recruiting Room Upgrades , UA# 085-18-1485

Planning is complete for a water outage at the Mal Moore Athletic Facility in order to install isolation valves to allow for work associated with the subject project. This outage is scheduled for today, Thursday, May 10th, 2018 from 6:00 PM to 9:00 PM. Notes: • Shawn Templeton is aware • This will impact domestic water only […]

Electrical Shutdown – Lakeside Dining Hall, UA Electrical Maintenance

An electrical shutdown at Lakeside Dining Hall has been scheduled to perform electrical maintenance.   This shutdown is scheduled for tonight, Thursday, May 17th, 2018 from 6:00 PM to 10:00 PM.   Notes: • The building is currently closed for the dining hall renovation project • Dunkin Donuts is closed for the summer so their operations won’t […]

Electrical Shutdown – Bryce Lawn Apartments, UA Electrical Maintenance

An electrical shutdown is scheduled for the Bryce Lawn Apartments in order to perform preventive maintenance.This shutdown is scheduled for tomorrow morning, May 25th, 2018 from 6:00 AM to 12:00 PM. Notes: • UA Facilities to verify all equipment is operational once power is restored • UA Housing is aware and prepared for shutdown • Ricky Luker to […]

Electrical Shutdown – Mal Moore Athletic Facility Dining Addition, UA# 085-16-953

The generator for the Mal Moore Dining Addition needs to be tested again.This is scheduled for tomorrow morning, May 25th, 2018 from 8:00 AM to 10:00 AM. Notes: • The power to Mal Moore Athletic Facility will be off momentarily until the new generator responds with emergency power.  Once on emergency power, building systems should operate […]