Planning is complete for an upcoming electrical shutdown of the University Services Campus.
• Impacted buildings include:
o All buildings north of Ruby Tyler Pkwy
o F.C. White Food Service building and Wallace Educational building which are on the south side of Ruby Tyler Pkwy
o The New Kitchen for Bryce and the Main Bryce Hospital will not be impacted
This electrical shutdown is scheduled to start on Saturday, April 14th, 2018 at 7:00 AM and will end on Sunday, April 15th, 2018 at 7:00 PM.
Notes for buildings currently in-use:
• Business Activities Center
o Has back-up emergency generator
o Fire alarm system on generator and battery back-up and will remain operational
o Building is sprinkled and on city water pressure
o Sewer pump for the west bathrooms is not on the emergency back-up system. These bathrooms do not need to be used
• Procurement Services
o Has back-up emergency generator
o Fire alarm system on generator and battery back-up and will remain operational
o Building is sprinkled and on city water pressure
o No other concerns
• Ruby Tyler Hall
o Not on emergency back-up power
o FA system on 24 hour battery back-up and will remain operational until batteries are depleted
o Building is sprinkled and on city water pressure
o No other concerns
• New Automotive Services
o Has back-up emergency generator
o Fire alarm system on generator and battery back-up (Kelton K./GC to connect FA panel to temp. generator on Cottage 8 in order to keep Automotive Services in the network loop. Coordinate with EHS)
o Building is sprinkled and on city water pressure
o No other concerns
• Bus Maintenance Garage
o Has back-up emergency generator
o Fire alarm system on generator and battery back-up and will remain operational
o Building is sprinkled and on city water pressure
o No other concerns
• Bus Fueling Station
o Has back-up emergency generator
• Cottage 8 (Equestrian)
o Not on emergency back-up power
o FA system on 24 hour battery back-up (This FA panel will have a temp. generator connected will remain operational)
o Building is sprinkled and on city water pressure
o No other concerns
• Cottage 9 (Const. Admin.)
o Not on emergency back-up power
o FA system on 24 hour battery back-up and will remain operational until batteries are depleted
o Building is sprinkled and on city water pressure
o No other concerns