Electrical Shutdown – Lakeside Dining Hall, UA Electrical Maintenance

  • October 8th, 2018
  • in

An electrical shutdown at Lakeside Dining Hall has been scheduled to perform electrical maintenance.  
This shutdown is scheduled for tonight, Thursday, May 17th, 2018 from 6:00 PM to 10:00 PM.
 
Notes:
• The building is currently closed for the dining hall renovation project
• Dunkin Donuts is closed for the summer so their operations won’t be impacted.  All cold storage items has been moved elsewhere so freezers won’t be an issue
• UA Elevator has shutoff and secured the elevators
• Ricky Luker to submit work orders to shops that request one

Water Outage – Mal Moore Athletic Facility Recruiting Room Upgrades , UA# 085-18-1485

  • October 8th, 2018
  • in

Planning is complete for a water outage at the Mal Moore Athletic Facility in order to install isolation valves to allow for work associated with the subject project. This outage is scheduled for today, Thursday, May 10th, 2018 from 6:00 PM to 9:00 PM.
Notes:
• Shawn Templeton is aware
• This will impact domestic water only
• UA Plumbing to shutoff water and restore water once work is complete
• UA Plumbing to perform walk-thru of building once water is restored
• Contractor to drain system
• Contractor to contact UA Plumbing evening shift when work is complete and water can restored.  (205) 703-3239
• Chad Elliott to submit work order to UA Plumbing immediately

Electrical Shutdown – Bryce Lawn Apartments, UA Electrical Maintenance

  • October 8th, 2018
  • in

An electrical shutdown is scheduled for the Bryce Lawn Apartments in order to perform preventive maintenance.This shutdown is scheduled for tomorrow morning, May 25th, 2018 from 6:00 AM to 12:00 PM.
Notes:
• UA Facilities to verify all equipment is operational once power is restored
• UA Housing is aware and prepared for shutdown
• Ricky Luker to submit work orders to shops upon request

Electrical Shutdown – Bryant Denny Stadium , UA Electrical Maintenance

  • October 8th, 2018
  • in

This will impact power to the entire stadium.**The Digital Media Center will be brought back online by the emergency power system throughout the duration of the shutdown.  However, the Digital Media Center may encounter a brief power outage at the start and end times of the shutdown.  If this is an issue, the Digital Media Center representative will need to contact Ricky Luker with UA Electrical at 348-3961.
** Daniel Black to verify if all broadcast equipment is on UPS.
Notes:
• This will impact all electrical and mechanical systems
• BDS is on 7 back-up emergency generators
• The Emergency Operations Center will be impacted (EOC is on the back-up emergency system)
• Fire Alarm system is on back-up emergency system
• BDS has (2) fire pumps
• Chillers for the north zone and south zone will be impacted
• West elevators will be out of operation. North, south and east elevators are on the back-up emergency system (Digital Media Center to use Northeast elevators)
• Camera systems/monitoring equipment will be ok per Michael Kelley (note from prior shutdown)
• Access control will not be operational.  Not on emergency system
• The gate control for Zoe’s on south end will be impacted (Shawn T. to raise for the weekend)
• The OIT data closet by the home team locker room is not on the emergency system. No other buildings should be impacted (note from prior shutdown)
Action Items:
• 2 fire pumps impacted – South and East Sides – East side fire pump is on back-up emergency system.  UA Plumbing to verify if the south side fire pump is on the emergency system.  If not, UA Electrical to coordinate with Security Resources about performing fire watch
• UA Plumbing shop to verify if plumbing equipment (booster pumps, sump and grinder pumps, water heaters, ect.) are on the emergency system.  If not, is generator needed? (ask Terry McMillan with UA Electrical)
• UA HVAC to shutdown all mechanical equipment and start-up once power is restored
• UA Elevator Maint. to shutoff and secure all elevators that will not remain operational.  Verify start-up once power is restored
• UA Electrical to notify Stephen Lake 30 min prior to restoring normal power in order to test transfer switch functionality for east elevators
• Shawn Templeton to coordinate with Zoe’s Kitchen
• Due to security risk, building signage will not be posted
• Ricky Luker to submit work orders to shops for building support upon request

Electrical Shutdown – Mal Moore Athletic Facility Dining Addition, UA# 085-16-953

  • October 8th, 2018
  • in

The generator for the Mal Moore Dining Addition needs to be tested again.This is scheduled for tomorrow morning, May 25th, 2018 from 8:00 AM to 10:00 AM.
Notes:
• The power to Mal Moore Athletic Facility will be off momentarily until the new generator responds with emergency power.  Once on emergency power, building systems should operate as normal
• UA Facilities to verify all equipment comes on during shutdown and afterwards once normal power is restored
• UA Facilities and Athletics are both aware
• Alison F. to submit work orders to UA HVAC, UA Electrical

Electrical Shutdown – University Services Campus Medium Voltage Upgrades , UA# 000-15-377

  • October 8th, 2018
  • in

Planning is complete for an upcoming electrical shutdown of the University Services Campus.• Impacted buildings include:
o All buildings north of Ruby Tyler Pkwy
o F.C. White Food Service building and Wallace Educational building which are on the south side of Ruby Tyler Pkwy
o The New Kitchen for Bryce and the Main Bryce Hospital will not be impacted
This electrical shutdown is scheduled for Saturday, June 9th, 2018 from 7:00 AM to 12:00 PM.
Notes for buildings currently in-use:
• Business Activities Center
o Has back-up emergency generator
o Fire alarm system on generator and battery back-up and will remain operational
o Building is sprinkled and on city water pressure
o Sewer pump for the west bathrooms is not on the emergency back-up system.  These bathrooms do not need to be used
o No other concerns
• Procurement Services
o Has back-up emergency generator
o Fire alarm system on generator and battery back-up and will remain operational
o Building is sprinkled and on city water pressure
o No other concerns
• Ruby Tyler Hall
o Not on emergency back-up power
o FA system on 24 hour battery back-up and will remain operational
o Building is sprinkled and on city water pressure
o No other concerns
• New Automotive Services
o Has back-up emergency generator
o Fire alarm system on generator and battery back-up
o Building is sprinkled and on city water pressure
o No other concerns
• Bus Maintenance Garage
o Has back-up emergency generator
o Fire alarm system on generator and battery back-up and will remain operational
o Building is sprinkled and on city water pressure
o No other concerns
• Bus Fueling Station
o Has back-up emergency generator
• Cottage 8 (Equestrian)
o Not on emergency back-up power
o FA system on 24 hour battery back-up
o Building is sprinkled and on city water pressure
o No other concerns
• Cottage 9 (Const. Admin.)
o Not on emergency back-up power
o FA system on 24 hour battery back-up and will remain operational
o Building is sprinkled and on city water pressure
o No other concerns
General notes:
• UA Facilities to verify start-up of equipment once power is restored
• All computers will need to be powered down prior to start of shutdown
• Alison Ferrer to submit work orders to UA HVAC, UA Elect, UA Plumb

Kelton Kite to contact personnel from each shop when power is being restored:
UA Plumb: 205-561-4148
UA HVAC: 205-361-2124
UA Elect: 205-210-1738

Electrical Shutdown – Bicycle Shop Operation Center Demolition , UA# 424-17-1246

  • October 8th, 2018
  • in

Planning is complete for an upcoming electrical shutdown in order to remove power to the Bicycle Shop Operation Center to allow for demolition.This shutdown is scheduled for Wednesday, June 6th, 2018 from 5:00 AM to 8:00 AM, but could end sooner.
This will impact power to EHS, Student Media and the Theater and Dance buildings.
Notes:
• UA Electrical is aware and will perform the disconnection
• Student Media is on back-up emergency generator and all equipment will stay operational
• Student Media fire alarm system is on the emergency generator and will remain operational
• EHS & Theater and Dance do not have a back-up emergency generator but fire alarm systems are on battery back-up and will remain operational
• UA HVAC to verify all A/C equipment is operational once power is restored to EHS, Student Media, & Theater and Dance

Gas Outage – Capstone Parking Deck, UA# 680-15-363

  • October 8th, 2018
  • in

Planning is complete for an upcoming gas outage in order to relocate an existing gas line that is in conflict the installation of a storm drain for the captioned project.This outage is scheduled for Thursday, June 14th, 2018 from 7:00 AM to 5:00 PM.
This will impact gas service to Moody Music Building, Bryant Conference Center and Bryant Museum.
Notes:
• This will impact the domestic (hot) water
• This will impact building reheat for all 3 buildings. Slightly lower building temps should be expected
• UA Plumbing to shutoff/turn on gas at closest valve
• UA Plumbing and UA HVAC will restart all gas equipment once work is complete

Electrical Shutdown – University Hall Renovation , UA# 420-17-1006

  • October 8th, 2018
  • in

Planning is complete for an upcoming electrical shutdown for the University Hall Renovation project.This shutdown is scheduled for Saturday, July 21st, 2018 from 7:00 AM to 12:00 PM.
This will impact normal power to Capital Hall, Bryant-Jordan Hall, the Bryce Main and old Superintendents building.
Notes:
• UA Electrical to coordinate “hot ties” with Alabama Power.  This allows for isolation of only the buildings noted above.  The Harper Center on Bryce campus will not be impacted
• Capital Hall
o Has back-up emergency generator
o Fire alarm system is on emergency generator and will remain operational
o Fire pump is on emergency generator so the fire sprinkler system will remain operational
o UA HVAC to shutoff and restart equipment
o UA Plumbing – No items of concern noted
o UA Elevator to shutdown and secure the elevators
o Access control (card access) on west side of building will not be operational
o All computers need to be powered down prior to electrical shutdown
• Bryant-Jordan Hall
o Fire Alarm system is on battery back-up and will remain operational
o UA HVAC to shutoff and restart equipment
o UA Plumbing – No items of concern noted
o All computers need to be powered down prior to electrical shutdown
• UA Facilities to perform walk-thru of both buildings once power is restored

Electrical Shutdown – University Hall, UA# 420-17-1006

  • October 8th, 2018
  • in

This shutdown has been rescheduled for Thursday, June 14th, 2018 from 1:00 PM to 5:00 PM.This will shutoff power to Bryant-Jordan Hall, Bryce Superintendents Building and will impact construction power to the main Bryce Hospital.
Notes:
• Fire Alarm system for Bryant-Jordan Hall is on battery back-up and will remain operational
• UA Facilities to perform walk-thru of Bryant-Jordan Hall once power is restored.
• No other concerns to other buildings noted.