Electrical Shutdown – Bidgood Hall Behavioral Lab 249, UA# 031-18-1504

  • October 8th, 2018
  • in

Planning is complete for an electrical shutdown at Bidgood Hall to test emergency lighting for the new Behavioral Lab 249.The shutdown is scheduled for Wednesday September 5th from 5:00 – 5:30 am.

Notes:
• The electrical shop did verify that the emergency generator is in service and functioning properly.
• The outage will effect Bidgood Hall and the Bruno Library.
• The outage will only effect normal power, anything on emergency power will not be effected.
• UA Electrical will perform the power shutdown.
• UA Electrical will have a generator tech on site during the shutdown.

Electrical Shutdown Coordination – Tutwiler Parking Deck (UA# 782-16-951) , SW Campus Utilities and Infrastructure (UA# UTL-17-1016)

  • October 8th, 2018
  • in

An electrical shutdown has been planned for the Tutwiler Parking Deck in order for Alabama Power Co. to convert their overhead lines to underground along the north side of 12th St.This work is scheduled to take place on Wednesday, September 12th, 2018 from 8:00 AM to 3:00 PM.  The Tutwiler Parking Deck will be without normal power for approx. 3 hours within this timeframe.
If weather does not permit for 9/12, then this work will take place on 9/13 during the same time.
Notes:
• The Tutwiler Parking Deck has a back-up emergency generator and will remain operational
• UA Transportation Services to open gate arms prior to shutdown if needed

Electrical Shutdown – Bryant Denny Stadium , UA Electrical Maintenance

  • October 8th, 2018
  • in

An electrical shutdown has been scheduled for BDS in order for UA Electrical to install additional meters for gameday monitoring.This shutdown is scheduled for tomorrow, Wednesday, September 26th, 2018 from 5:00 AM to 9:00 AM.
This will NOT impact power to the Digital Media Center and the North Zone.
Notes:
• This will impact all electrical and mechanical systems
• BDS is on 7 back-up emergency generators
• The Emergency Operations Center will be impacted (EOC is on the back-up emergency system)
• Fire Alarm system is on back-up emergency system
• BDS has (2) fire pumps
• Chillers for the south zone, and east and west sides will be impacted
• West elevators will be out of operation. North, south and east elevators are on the back-up emergency system
• Camera systems/monitoring equipment will be ok per Michael Kelley (note from prior shutdown)
• Access control will not be operational.  Not on emergency system
• The gate control for Zoe’s on south end will be impacted
• The OIT data closet by the home team locker room is not on the emergency system. No other buildings should be impacted (note from prior shutdown)
Action Items:
• 2 fire pumps impacted – South and East Sides – East side fire pump is on back-up emergency system.  UA Plumbing to verify if the south side fire pump is on the emergency system
• UA Plumbing shop to verify if plumbing equipment (booster pumps, sump and grinder pumps, water heaters, ect.) are on the emergency system.  If not, is generator needed? (ask Terry McMillan with UA Electrical)
• UA HVAC to shutdown all mechanical equipment and start-up once power is restored
• UA Elevator Maint. to shutoff and secure all elevators that will not remain operational.  Verify start-up once power is restored
• UA Electrical to notify Stephen Lake 30 min prior to restoring normal power in order to test transfer switch functionality for east elevators
• Shawn Templeton to coordinate with Zoe’s Kitchen
• Due to security risk, building signage will not be posted
• Ricky Luker to submit work orders to shops for building support upon request